Dear all I have 2 pbs in the same lan, one is for synching backups from the other one. So I'm using the remote synch job and I have set the option transfer last 7, but every day I see the number of backups incrementing instead of stay to seven, but is not transfering the same number of the backups that I have in the remote dataset that is huge, so somehow is limiting the number of backups. To fix this I'm using prune set to latest 7 and gc jobs, but Perhaps I am interpreting the meaning of this function incorrectly?
Just a point, since the title of transfer last says "The maximum amount of snapshots to be transferred (per group)" I tried to made 2 groups one type ct and one type vm to include everything but this didn't changed anything.