Hi,

The backup jobs run during the night between 23:00 and roughly 7:00.

When configuring the schedule for verify jobs, prune jobs and garbage collection I only have a limited choice of hours that will conflict with the running jobs:

prune-schedule.png

Is it possible to extend that list so that these jobs will run only during the day where the PBS is otherwise idle?
 
This is a text field, and you can add arbitrary text there - not limited to the values in the list.